ABI: Project “Construction and Technical Adaptation to the Sin of the Central System Tarija ”fails to be completed by neighboring resistance The General Manager of ENDE TRANSMISIÔN, filial of Ende Corporation, Ing. Filiberto Soto clarified that “the company reached 99.44% of the physical execution of the project‘ Construction and Technical adaptation to the Sin of […]

ABI: Project “Construction and Technical Adaptation to the Sin of the Central System Tarija ”fails to be completed by neighboring resistance
The General Manager of ENDE TRANSMISIÔN, filial of Ende Corporation, Ing. Filiberto Soto clarified that “the company reached 99.44% of the physical execution of the project‘ Construction and Technical adaptation to the Sin of the Central Tarija ’system.To date, 160 meters of ditches and installation of pipelines for the laying of the underground line that was paralyzed due to the resistance of Neighbors of Spain Street in the city of Tarija ”.