ENDE CORPORACIÓN: SOON BOLIVIA WILL STRENGTHEN ITS ELECTRICAL SYSTEM WITH THE SECOND LINE IN EXTRA HIGH TENSION THAT WILL ALLOW REGIONAL ENERGY INTEGRATION UNICOM ENDE / 11-07-2024.- The National Electricity Company (ENDE) Corporation, advances in the construction of its Second Transmission Line in 500 Kilovolts (KV), called “Carrasco – The Gaps and Substations Associated “. […]

ENDE CORPORACIÓN: SOON BOLIVIA WILL STRENGTHEN ITS ELECTRICAL SYSTEM WITH THE SECOND LINE IN EXTRA HIGH TENSION THAT WILL ALLOW REGIONAL ENERGY INTEGRATION

UNICOM ENDE / 11-07-2024.- The National Electricity Company (ENDE) Corporation, advances in the construction of its Second Transmission Line in 500 Kilovolts (KV), called “Carrasco – The Gaps and Substations Associated “. This important project located from the department of Cochabamba to Santa Cruz, will strengthen the transport electric in extra high voltage to the eastern region of the country and will allow Bolivia to integrate electrically with Brazil.

fn-10072024-4

The execution of the project is in charge of Ende Transmission.To date, the assembly of the Line reactors In Carrasco substations and gaps, which represents a general advance of 86%.

This line has an approximate extension of 188 kilometers and connects the central and eastern areas of the System National interconnected (SIN), constituting an energy corridor that will strengthen the electricity and will guarantee a reliable supply for industry, health, education and growing populations that increased Your demand in the last years.

To its conclusion, the Carrasco electric line – Las Greas in 500 kV will meet all the technical characteristics For the National Government, through Ende Corporation, to face interconnection projects With countries neighbors, allowing Bolivia to export electricity to countries like Brazil, positioning itself as Key actor in The regional energy market.

Engineering and labor used in the construction of this project in its two components (line and substations), is in charge of Bolivian professionals in its entirety, the result of the constant training carried out by transmission to its technical personnel in electrical transport issues, which It allows to form equipment with specialized and trained personnel to face this type of work.