On the 148th anniversary of the Autonomous Region of the Great Chaco, the president of the Plurinational
State of
Bolivia, Luis Arce, through a ch´alla, made the official delivery of the “Construction Line Construction
Electric 69 kV Yaguacua – Caraparí ”, which will connect to the Chaco municipality of Caraparí to the
system
National interconnected (SIN), benefiting their communities, which from the date may count
With safe, reliable and from different sources of electricity generation.
This project is part of the investments made by the National Government to increase the
Electrical coverage in the country, benefits 3,592 families from the communities of the second section
of the
Gran Chaco – Caraparí and had an investment 58 million Bolivians.
The project was executed by Ende Transmission, as a service to the Regional Autonomous Government of the
Gran
Chaco – Caraparí.The scope consisted of the construction of more than 30 kilometers of line in high
voltage in 69 kV, which joins the Yaguacua substation, adjacent to the southern thermoelectric plant and
the
New Caraparí substation at 69/24.9 kV and has 2 12.5 mva transformers, plus one
Lot of medium voltage cells at 24.9 kV.
The investment made allowed the existing subsystem connection in Caraparí to the system
National interconnected, which allows to expand coverage, improve the quality of the service, reduce
interruption rates and restitution times, in addition to reducing loss rates from
energy.
The national government continues to incorporate electrical infrastructure that allows you to illuminate
the homes of
communities where this basic service did not exist before, it also reinforces the electrical system for
Optimize the service, allowing to considerably decrease the probability of electric cuts
In our country.