• December 24, 2021
    SPUTNIK: Bolivia reports progress in electrical interconnection with Argentina
    Bolivia is about to conclude the laying of an interconnection network with Argentina, in order to probably initiate the export of electricity to the neighboring country, The National Electricity Company (ENDE) reported.
  • December 23, 2021
    CONSTRUCCIÓIN LATINOAMERICANA: Bolivia-Argentine transmission line with 86% Advance
    The national electricity company (ENDE Corporation), through its subsidiary ENDE Argentine transmisión (Etasa), has resumed in recent weeks the construction of the section, in territory Argentine, from the power line that is part of the “Juana Azurduy of Padilla 132 KV Bolivia – Argentina “So far, the works are 86% of progress, which, once the Project, will allow Bolivia to export about 120 energy megawatts.In this context, for Evaluate the progress of this project, in recent days they met in the Argentine province of Salta the Executive President of Ende Corporación, Marco Escobar, and the Minas and Energy Secretary of Salta, Flavia Rojón
  • December 22, 2021
    AHORA EL PUEBLO: Advance the electric integration project between Bolivia and Argentina
    The construction of the power line in the Argentine territory, which is part of the Juana Azurduy of Padilla 132 KV Bolivia – Argentina, records an advance of 86%, reported yesterday The National Electricity Company (ENDE) Corporation).Ende, through your subsidiary company ENDE Transmisión Argentina SA (Etasa), resumed the construction of the section in Argentine territory in 2021.
  • ENERGÍA BOLIVIA: Padilla Juana Azurduy power line has 86% of Advance
    The National Electricity Company (Ende Corporación), through your company Subsidiary Ende Argentine transmisión S.A.(Etasa), resumed the construction of the section in territory in 2021 Argentine of the power line that is part of the project “Juana Azurduy of Padilla 132 KV Bolivia – Argentina “and to date, it registers an advance of 86%. This work will allow Bolivia to export approximately 120 power megawatts to the neighboring country.Last week gathered in Salta, Argentina, the president Executive of Ende Corporación, Marco Escobar, and the Ministry and Energy Secretary of Salta, Flavia Rojón, To present the progress of this project.
  • LA RAZÓN: The construction of the Bolivia-Argentina power line has an advance of 86%
    With the prospect of exporting 120 energy megawatts to Argentina, where Corporation resumed the construction in Argentine territory of the electric line that is part of the Project “Juana Azurduy de Padilla”.To date, the work registers an advance of 86%.The national company of Electricity (Ende Corporación), through its subsidiary company Ende Argentina Transmisión (Etasa), he resumed the construction of the stretch in the past weeks, in Argentine territory, of the power line that It is part of the “Juana Azurduy of Padilla 132 KV Bolivia – Argentina” project.
  • December 21, 2021
    ABI: Transmission line that will export electricity to Argentina presents 86% of progress
    The “Juana Azurdu Padilla” transmission line, which will allow exporting energy electric to the Republic of Argentina, presents an advance of 86%, the national company reported on Tuesday of electricity (Ende Corporación).”Ende Corporation, through your subsidiary company Ende Transmission Argentina S.A.(Etasa), resumed in 2021 construction, in Argentine territory, of the power line that is part of the Juana Azurduy project of Padilla 132 KV Bolivia – Argentina, which registers a Advance of 86 percent, “the entity indicated through a press report.
  • PRENSA LATINA: Bolivian line advances to export electricity to Argentina
    La Paz, Dec 21 (Latin Press) The electricity transmission line Juana Azurduy of Padilla, through which Bolivia will export that energy to Argentina, it is 86 percent of Installation, a state fountain reported today.The project will allow you to transmit about 120 megawatts Power to the neighboring country, through a line of 120.4 kilometers between substations from both countries, he added In a report, the National Electricity Company (ENDE).The work contemplates a line in the Andean nation of 132 kilowatts that was already concluded, and another similar from the Argentine side, in the termination phase, adds the document.
  • LA VOZ DE TARIJA: Ende: transmisión line that will allow export electricity to Argentina presents 86% of progress
    The “Juana Azurdu Padilla” transmission line, which will allow exporting energy electric to the Republic of Argentina, presents an advance of 86%, the national company reported on Tuesday of electricity (Ende Corporación).”Ende Corporation, through your subsidiary company Ende Transmission Argentina S.A.(Etasa), resumed in 2021 construction, in Argentine territory, of the power line that is part of the Juana Azurduy project of Padilla 132 KV Bolivia – Argentina, which registers a Advance of 86 percent, “the entity indicated through a press report.
  • December 18, 2021
    EL DEBER: Salta highlights the electric interconnection project with Bolivia that will enter operation in 2022
    In Salta (Argentina) highlight the progress of the project of the electrical interconnection, of 132 kV, between the Yaguacua thermal power plant (Tarija) with the Tartagal Transformer station, in Argentine territory, who will enter into operation the first quarter of 2022. The Ministry of Mining and Energy of the Salteña Government, Flavia Royon, said that this work is important because it will stabilize the Electrical supply to the General Department San Martín.
  • EJU TV: Salta highlights the electric interconnection project with Bolivia that will enter operation in 2022
    It is sought that the interconnection from the south of the country allows the provision of energy Electric to distant and isolated locations in the province of Northern Argentine.In Salta (Argentina) Highlight the progress of the electric interconnection project, 132 kV, between the thermal power plant Yaguacua (Tarija) with Tartagal Transformer station, in Argentine territory, who will enter OPERATION The first quarter of 2022.