April 1, 2024 08:00

EJU: Ende reports 77% progress in the second line of electric transmission in extra high country tension The National Electricity Company (Ende Corporation) faces the construction of the “Transmission line in 500 kilovolts (KV) Carrasco – the associated gaps”, being The second line of electric transmission in extra high voltage of Bolivia, which to date […]

EJU: Ende reports 77% progress in the second line of electric transmission in extra high country tension
The National Electricity Company (Ende Corporation) faces the construction of the “Transmission line in 500 kilovolts (KV) Carrasco – the associated gaps”, being The second line of electric transmission in extra high voltage of Bolivia, which to date reports a breakthrough 77%.