• October 6, 2022
    LOS TIEMPOS: Initiative.IMPRESS CALL ROULY SOLAR 2022 FOR DESIGNS OF hybrid cars
    The Feicobol and Immersive SRL Consultive Group Foundation yesterday issued the CALL OF THE BOLIVIA SOLAR RALLY 2022. According to the call, those interested in participating in the First stage of the competition can be registered until October 15.Participants must compete with a hybrid car, with the design of giving way to the development of renewable energy no conventional.
  • September 30, 2022
    EL PERIÓDICO: Bs 120 million are released by debt with ENDE
    (El periódico-September, 30/2022) The governor of the department of Tarija, Oscar Montes Barzón, public opinion informed Thursday that Justice determined to release Bs 122 millions that were retained in accounts of said body as a precautionary measure by debt pending with the National Electricity Company (ENDE).
  • September 29, 2022
    GOBERNACIÓN DE TARIJA: Governorate analyzes project without executed by ENDE
    The governor of the department of Tarija, Lic. Oscar Montes Barzón, reported that the Departmental Executive analyzes the contract between the Autonomous Departmental Government of Tarija (GADT) signed by former interim governor Lino Condori, with the National Electricity Company (ENDE) for the Construction of the Tarija connection project to the National Interconnected System (SIN) and the possibility of auditing the entire project.
  • EL PAÍS: Tarija: Governorate analyzes project without executed by Ende
    The governor of the department of Tarija, Lic. Oscar Montes Barzón, reported that the Departmental Executive analyzes the contract between the Autonomous Departmental Government of Tarija (GADT) signed by former interim governor Lino Condori, with the National Electricity Company (ENDE) for the Construction of the Tarija connection project to the National Interconnected System (SIN) and the possibility of auditing the entire project.
  • September 27, 2022
    NEW South: Government canceled debt to the interconnected to Sin
    The governor of the department of Tarija, Lic. Oscar Montes Barzón, confirmed that canceled the debt to the National Electricity Company (ENDE) for the connection to the National Interconnected System (SIN) with the loan obtained from private banking, for an amount of 122 million Bolivians, therefore, departmental authorities hope justice return the resources retained to the accounts of the Departmental Autonomous Government (GADT) to give continuity to the departmental programs and projects.
  • September 26, 2022
    PLUSTLT: Government canceled debt to the interconnected to without
    The governor of the department of Tarija, Lic. Oscar Montes Barzón, confirmed that canceled the debt to the National Electricity Company (ENDE) for the connection to the National Interconnected System (SIN) with the loan obtained from private banking, for an amount of 122 million Bolivians, therefore, departmental authorities hope justice return the resources retained to the accounts of the Departmental Autonomous Government (GADT) to give continuity to the departmental programs and projects.
  • EL PAíS: After paying Ende, the Government of Tarija asks for the return of the retained resources
    The governor of the department of Tarija, Oscar Montes Barzón, confirmed that he was canceled the Debt to the National Electricity Company (Ende ) for the connection to the system National interconnected (SIN) with the loan that was obtained from private banking, for an amount of 122 Millions of Bolivians.Therefore, he now expects justice to return the resources retained to accounts of the Departmental Autonomous Government (GADT) to continue programs and projects Departmental
  • September 16, 2022
    ENERGY PRESS: Camiri interconnects without
    Had an investment of $ 34.2 million and the project includes a line of transmission with a length of 125 km, the extension of the Padilla substation and the Construction of new substations in Monteagudo and Camiri. President Luis Arce Catacora, the Minister of Hydrocarbons and Energies, Franklin Molina Ortiz, and the president of Ende Corporation, Manuel Valle Vargas, inaugurated the interconnection of Camiri, in the department of Santa Cruz, to the System National interconnected (SIN), benefiting more than 16,000 families in the municipality with the improvement of the electric supply, in addition to extending electricity coverage, on the way Universalize the service.
  • ENERGÍA BOLIVIA: In The Anniversary Month of Santa Cruz, the National Government strengthens the electricity supply of Camiri With its interconnection to without
    President Luis Arce Catacora, the Minister of Hydrocarbons and Energies, Franklin Molina Ortiz, Y The president of Ende Corporation, Manuel Valle Vargas, opened on Thursday the interconnection De Camiri, in the department of Santa Cruz, to the National Interconnected System (SIN), benefiting plus of 16,000 families of the municipality with the improvement of the electricity supply, in addition to extend the Electricity coverage, on the way to universalize the service.
  • September 15, 2022
    AHORA EL PUEBLO: Camiri se integrates the National Electricity Interconnected System
    With an investment of $ 34.2 million, President Luis Arce delivered this afternoon the Interconnection plant Electric of the National Interconnected System (SIN) in the municipality of Camiri, department of Holy Cruz, to guarantee the supply of electricity to 16 thousand families.”Today We deliver This interconnection to the national integrated system that has a very important impact for all your Here in Camiri.First electricity today will be continuously and permanently, as in all of the country that is inerted to SIN, “said Arce in the act of opening which was carried out as part of the agenda for the 212 years of anniversary of Santa Cruz.