ENDE TRANSMISIÓN CONCLUDED ELECTRICAL LINE THAT ALLOWS CONNECTION TO THE SIN OF THE EL DORADO WIND FARM. ENDE Transmisión S.A., subsidiary of ENDE Corporación, in this management concluded the execution of the project “Transmission Line 230 kV Brechas – El Dorado”, which allows the injection to the National Interconnected System (SIN) of the electrical energy […]

ENDE TRANSMISIÓN CONCLUDED ELECTRICAL LINE THAT ALLOWS CONNECTION TO THE SIN OF THE EL DORADO WIND FARM.

ENDE Transmisión S.A., subsidiary of ENDE Corporación, in this management concluded the execution of the project “Transmission Line 230 kV Brechas – El Dorado”, which allows the injection to the National Interconnected System (SIN) of the electrical energy generated by the “El Dorado Wind Farm ”, The largest in Bolivia with an installed capacity of 54 MW generated through the 15 installed wind turbines that are located south of the city of Santa Cruz de la Sierra, in the municipality of Cabezas

The scope of ENDE Transmisión included the construction of the corresponding expansions in the Brechas and El Dorado electrical substations in 230 kV, as well as the construction of 51.15 km of electric transmission line in complete double triple with two conductors per phase

This important project is part of the national strategy to transform the energy matrix, which contributes to the execution of renewable energy projects, in order to displace the use of gas and diesel for electricity generation. Thus reducing the environmental impact and facilitating, for example, that the gas can be destined to export markets for commercialization at a better price.