December 7, 202115:48

ABI: ENDE Transmisión concludes the electric line that allows the connection of the El Dorado wind farm to the SIN ENDE Transmisión S.A., a subsidiary of ENDE Corporación, concluded the execution of the project “230 kV Transmission Line Las Brechas – El Dorado”, which allows the injection of the energy generated by the El Dorado […]

ABI: ENDE Transmisión concludes the electric line that allows the connection of the El Dorado wind farm to the SIN
ENDE Transmisión S.A., a subsidiary of ENDE Corporación, concluded the execution of the project “230 kV Transmission Line Las Brechas – El Dorado”, which allows the injection of the energy generated by the El Dorado wind farm into the National Interconnected System (SIN). The El Dorado wind farm, recently inaugurated by President Luis Arce Catacora, is considered the largest in Bolivia, since it has an installed capacity of 54 megawatts (MW), generated through the 15 wind turbines, installed in the south of Santa Cruz, in the municipality of Cabezas.