ENDE TRANSMISiÓN COMMITTED TO THE GROWTH OF THE BOLIVIAN TRANSMISSION NETWORK, EXECUTES IMPORTANT PROJECTS ENDE Transmisión SA, a subsidiary of ENDE Corporación, with the purpose of expanding and strengthening the transmission network in the National Interconnected System (SIN), in recent years, between the 2016 and 2021 administrations, has built 2,027.81 kilometers of lines transmission in […]
ENDE TRANSMISiÓN COMMITTED TO THE GROWTH OF THE BOLIVIAN TRANSMISSION NETWORK, EXECUTES IMPORTANT PROJECTS
ENDE Transmisión SA, a subsidiary of ENDE Corporación, with the purpose of expanding and strengthening the transmission network in the National Interconnected System (SIN), in recent years, between the 2016 and 2021 administrations, has built 2,027.81 kilometers of lines transmission in high and extra high voltage: 364.15 km at 115 kV; 46.3 at 132 kV; 1,470.58 km at 230 kV and 146.78 km at 500 kV.
Next, the evolution graph in the construction of the transmission lines is presented:
N° |
PROJECTS DETAIL |
TENSION |
TOTAL PROYECT [km] |
2016 |
2017 |
2018 |
2019 |
2020 |
2021 |
---|---|---|---|---|---|---|---|---|---|
1 |
Línea Sucre – La Plata – Potosí |
115 |
112,36 |
112,36 |
– |
– |
|||
2 |
Línea Palca – Mazocruz 230kV |
230 |
72,00 |
72,00 |
– |
– |
|||
3 |
Línea Warnes – Brechas |
230 |
118,75 |
80,64 |
38,11 |
– |
|||
4 |
Línea Warnes – Urubó 230 kV |
230 |
20,96 |
13,20 |
7,76 |
– |
|||
5 |
Línea San José II – Santivañez 230 kV |
230 |
82,11 |
– |
82,11 |
– |
|||
6 |
Línea Caihuasi – Jeruyo 115 kV |
115 |
46,00 |
– |
46,00 |
– |
|||
7 |
Línea Mazocruz – Pallina 230 kV |
230 |
23,00 |
– |
23,00 |
– |
|||
8 |
Línea Uyuni – Planta Solar Uyuni 230 kV |
230 |
4,50 |
– |
4,50 |
– |
|||
9 |
División de línea Valle Hermoso – Catavi en Irpa Irpa |
115 |
1,20 |
– |
1,20 |
– |
|||
10 |
Subestación Villa Tunari 230 kV |
230 |
0,20 |
– |
0,20 |
– |
|||
11 |
Línea Bélgica – Los Troncos 230 kV |
230 |
103,58 |
– |
96,71 |
6,87 |
|||
12 |
Línea Huaji – Caranavi 115 kV |
115 |
74,45 |
– |
70,90 |
3,55 |
|||
13 |
Repotenciamiento Línea Vinto – Santivañez |
230 |
123,40 |
– |
– |
123,40 |
– |
– |
|
14 |
Línea Litio – Salar 115 kV |
115 |
81,50 |
– |
– |
81,50 |
|||
15 |
Línea de Transmisión Juana Azurduy de Padilla |
132 |
46,30 |
– |
– |
46,30 |
|||
16 |
Conexión al STI de Subestaciones Entre Ríos I y Entre Ríos II |
230 |
2,03 |
– |
– |
2,03 |
|||
17 |
Anillo Energético del Sur |
230 |
323,61 |
– |
– |
276,40 |
47,21 |
– |
– |
18 |
Adecuación Línea Warnes – Urubó 230 kV |
230 |
21,25 |
– |
– |
2,40 |
18,85 |
– |
– |
19 |
Conexión Solar Oruro al SIN |
230 |
50,10 |
– |
– |
– |
50,10 |
– |
|
20 |
Línea Arboleda – Las Lomas |
230 |
13,11 |
– |
– |
– |
13,11 |
– |
|
21 |
Conexión ECEBOL Potosí 115 kV al SIN |
115 |
4,50 |
– |
– |
– |
4,50 |
– |
|
22 |
Línea Warnes – Nueva Santa Cruz 230 kV |
230 |
13,50 |
– |
– |
– |
2,45 |
– |
|
23 |
Subestación Yapacaní 230 kV |
230 |
0,10 |
– |
– |
– |
0,10 |
– |
|
24 |
Subestación San Julián 230/115 kV |
230 |
1,03 |
– |
1,03 |
– |
– |
||
25 |
Segunda Terna Bélgica – Los Troncos 230 kV |
230 |
98,78 |
– |
– |
– |
98,78 |
– |
|
26 |
Línea Tarija – Angostura 115 kV |
115 |
44,17 |
– |
– |
17,70 |
12,30 |
13,35 |
0,79 |
27 |
Línea Brechas – El Dorado 230 kV |
230 |
51,15 |
|
|
– |
– |
16,02 |
35,13 |
28 |
Ampliación San José – Santivañez |
230 |
0,77 |
– |
– |
– |
– |
– |
0,77 |
29 |
Línea de Transmisión 230 kV Troncos – Guarayos – Trinidad |
230 |
383,25 |
|
|
– |
– |
– |
357,70 |
30 |
Línea Carrasco – Santivañez 500 kV y Subestaciones Asociadas |
500 |
233,10 |
– |
– |
– |
– |
29,61 |
117,17 |
TOTALES |
278,20 |
370,49 |
560,15 |
248,43 |
58,98 |
511,56 |
|||
TOTALES ACUMULADOS |
278,20 |
648,69 |
1.208,84 |
1.457,27 |
1.516,25 |
2.027,81 |
With the start-up of the transmission projects described, the achievements and benefits that have materialized, among others, are the following:
- The transmission system of the National Interconnected System (SIN) has been strengthened, with the execution of projects in the departments of La Paz, Santa Cruz, Tarija, Chuquisaca, Potosí and Cochabamba.
- The connection to the SIN of new generation plants, thus making it possible to dispose of the generated energy, making it possible for distributors to meet the growing demand in the regions.
- An underground high voltage line was installed to supply electrical energy to the Potassium Salts and Lithium Carbonate Plants, for the industrialization of the evaporite resources of the Uyuni salt flat, located in the Salar de Uyuni itself, building the underground line in highly corrosive soil.
- The first section of the 132 kV transmission line was completed for the international interconnection with Argentina, located in Bolivian territory, which will allow the sale of electricity to the neighboring country and will generate income for Bolivia.
- The country’s first two extra-high voltage lines, at 500 kV, are being built in the central section of the SIN, which will allow the transmission of power from current generation plants and those planned for the future, located in the central and eastern areas. , to supply the national demand, as well as the export market.