UNICOM/ENDE CORPORACIÓN: Electric transmission projects in Tarija, La Angostura and Bermejo They register more than 95% progress UCOM-MHE-ENDE-AETN-07-07-2022.- The Deputy Minister of Electricity and Alternative Energies, Edgar Caero, the vice president of the National Electricity Company (Ende Corp.), Mauricio Arevey, the Ende Transmission Manager, Filiberto Soto, and the Director of the Supervisory Authority of Nuclear […]

UNICOM/ENDE CORPORACIÓN: Electric transmission projects in Tarija, La Angostura and Bermejo They register more than 95% progress

UCOM-MHE-ENDE-AETN-07-07-2022.- The Deputy Minister of Electricity and Alternative Energies, Edgar Caero, the vice president of the National Electricity Company (Ende Corp.), Mauricio Arevey, the Ende Transmission Manager, Filiberto Soto, and the Director of the Supervisory Authority of Nuclear electricity and energy (AETN), Eusebio Aruquipa, verified this Thursday that the projects of electric transmission that are built in Tarija, La Angostura and Bermejo are in their Final stretch with more than 95% progress and it is expected that in the following weeks they will be inaugurated for Get into operation.

nf_01082022_1

“Bermejo will connect to the National Interconnected System (SIN), its electrical energy will no longer depend of an isolated system, and will receive electricity from all over Bolivia, from the centrals thermal, hydraulic, wind and solar that we have in the country and growth and development of this region, ”said Vice Minister Caero at a press conference after Perform an inspection of the works.

The authorities first inspected the transmission line 115 kilovolts (KV) Tarija – the Angostura, which will have a length of 44.17 kilometers (km) and that already has 96% advance. This project will allow the connection to the new window generation central La Ventolera and will provide an energy withdrawal node through the construction of the new 115 kV substation Angostura.

Subsequently, they verified the advance of the 115 kV transmission line La Angostura – Bermejo, which Record 95% and will allow the connection of the isolated electrical system of Bermejo, improving quality of the electric service in the region for the benefit of that population of Tarijeña.The project includes the Construction of a simple list of transmission of 138.10 km in length and construction of the new electrical substation for Bermejo.

The National Government invests approximately BS182 million for these projects, within the framework of the Universalization policy of basic services.