LA RAZÓN: ENDE Transmisión concludes assembly of structures of the line of electric transmission in 500 kV Carrasco – Santiváñez ENDE Transmisión, a subsidiary of Ende Corporation, concluded the assembly of high towers voltage that is part of the “Transmission Line in 500 KV Carrasco – Santiváñez and Substations Associated ”, which is currently executing […]
LA RAZÓN: ENDE Transmisión concludes assembly of structures of the line of
electric transmission in 500 kV Carrasco – Santiváñez
ENDE Transmisión, a subsidiary of Ende Corporation, concluded the assembly of high
towers
voltage that is part of the “Transmission Line in 500 KV Carrasco – Santiváñez and Substations
Associated ”, which is currently executing the company.“It is the first electric transmission line in 500
KV of Bolivia, is a historical milestone in the construction of this type of high voltage lines of great
transport capacity and a work that will position the country at the level of the electrical sector of the
countries
neighbors of the South American continent, ”said the general manager of Ende Transmission, Ing. Filiberto
Soto