April 1, 202410:17

UNICOM/ENDE CORPORACIÓN: ENDE REPORTS 77% PROGRESS IN THE CONSTRUCTION OF THE SECOND LINE OF ELECTRIC TRANSMISSION IN EXTRA HIGH VOLTAGE FROM THE COUNTRY UNICOM ENDE / 19-03-2024.- The National Electricity Company (Ende Corporation) faces the construction of the project “Transmission line in 500 kilovolts (KV) Carrasco – the associated gaps and substations”, being The second […]

UNICOM/ENDE CORPORACIÓN: ENDE REPORTS 77% PROGRESS IN THE CONSTRUCTION OF THE SECOND LINE OF ELECTRIC TRANSMISSION IN EXTRA HIGH VOLTAGE FROM THE COUNTRY

UNICOM ENDE / 19-03-2024.- The National Electricity Company (Ende Corporation) faces the construction of the project “Transmission line in 500 kilovolts (KV) Carrasco – the associated gaps and substations”, being The second line of electric transmission in extra high voltage of Bolivia, which to date reports an advance of 77% and will allow strengthen the electricity supply in the departments of Cochabamba and Santa Cruz, in addition to providing the capacity of Electric power transport needed to market, in the future, electricity to the neighboring country from Brazil.

nf_06032024_2

The project is in charge of Ende Transmission and includes the construction of a line of 186.30 kilometers long, From the Carrasco substation (extension), located in the municipality of Entre Ríos in the province Carrasco del Cochabamba Department, until the Las Grechas (new facilities) substation, located at 35 kilometers south of The city, close to the population of Basilio, in the Cordillera province of the department of Santa Cruz. Currently performs the construction of foundations, the assembly of structures and the laying of conductors in the line, as well as All civil works and equipment assembly in Carrasco substations and gaps.

The highlights of this second line in 500 kV is that, all the line designs and Substations associated, were carried out with an engineering of Ende Transmission, as well as in the execution of this work, it is used 100% national cut and labor technology, consolidating the capacity of professionals Bolivians in the field electric.

The line will allow the creation of a large capacity for electricity transport, which will interconnect The eastern and central areas of the National Interconnected System (SIN), strengthening the supply electric and allowing to have the generation surplus at the Las Grechas collector node, for the future export.

Ende will continue working to strengthen the national electrical system.With the construction of the Second line of electric transport in 500 kV, Bolivia consolidates its electrical system as one of the safest and Reliable of the South American region.