• December 13, 2021

    PROJECTS IN EXECUTION

    THE INVESTMENT BUDGET OF ENDE TRANS Transmisión S.A.approved by directory, formulated with the purpose of expanding and Strengthen the transmission network in the National Interconnected System (SIN), includes for management 2024 the Execution of 7 transmission projects according to established schedules, considering that the conclusion dates of them are planned for management 2024 and the next efforts in accordance with the programming of Medium term in the national interconnected system (2024-2028).

    PROJECT DESCRIPTION:
    img-1
    1. 500 KV CARRASCO TRANSMISSION LINE – ASSOCIATED GAPS AND SUBSTATIONS

    The project consists in the construction of a 500 kV transmission line of 186.3 km in approximate length, simple Terna with four -driver beam per phase separated at 1.1 m, with Type 750 mcm driver, which starts in the Carrasco substation, connecting with the substation the gaps.It also includes extensions in 500 kV in the Carrasco substations and gaps.

    This project will strengthen the electric transmission between the eastern and central areas of SIN, increasing the power transmission capacity in the trunk network of the system, also allowing the surplus of Generation in the collector node The export gaps.

    img-3
    2. BARS EXPANSION TARIJA 115 KV SUBSTATION

    The project consists of expanding the 115 kV courtyard bars of the Tarija Electric Substation (Monte Sud) for allow the installation of a power transformer 115/24.9 kV, 25 MW in the Tarija substation, by the agent of Electricity distribution of the region.

    3. THIRD WARNES BARS EXPANSION 115 KV

    The project will allow the installation of a power transformer 115/24.9 kV and its respective bay by of the EMDEECRUZ ELECTRICAL ENERGY DISTRIBUTION AGENT will also allow having an additional position for a Withdrawal with power cable.

    img-4
    img-5
    4. DIVISION LINE 230 KV VINTO – MAZOCRUZ AND NEW NEW SUBSTATION PATACAMAYA

    The project consists of the division of the Vinto – Mazocruz 230 kV line at 6 km southeast Patacamaya in the La Paz Department, as well as the construction of a 230 kV double list transmission line (0.8 km approximately), from the point of division to the new Patacamaya 230 kV electric substation, which also It is part of the scope of the project.

    The execution of this project will allow the construction of a new Patacamaya substation, which will allow the Local distributor have a new withdrawal point, to meet the growing demand of the region.

    5. TRANSMISSION LINE 115 KV GUANAY – APOLO AND ASSOCIATED APOLO AND SUBSTRIES

    The project consists of the construction of a 115 kV transmission line from the current Guanay substation to The new Apollo substation, of an approximate length of 115 km.

    The execution of this project will provide greater reliability and safety in the supply of electricity to the Apollo population and surrounding towns.

    img-6
    img-7
    6. 115 KV SAN BUENAVENTURA TRANSMISSION LINE – IXIAMAS AND ASSOCIATED SUBSTATIONS

    The project consists of the construction of a transmission line at 115 kV from the current San Buenaventura substation to the new iaxiamas substation, with an approximate length of 90 km.

    img-11
    7. AMPLIACIÓN DE BARRAS CONTORNO BAJO 115 kV El

    proyecto consiste en realizar la ampliación de barras en nivel de tensión 115 kV de la subestación eléctrica Contorno Bajo que permita la instalación de una bahía de línea o transformador por parte del agente de generación ENDE Guaracachi.

    La ejecución de este proyecto posibilitará la inyección de la energía eléctrica generada por la planta solar fotovoltaica Solar Contorno Bajo al SIN.