• October 4, 2022
    UNICOM/ENDE Transmisión: End Transmisión continues with risk prevention program in electric lines

    Fulfilling one of its Social Responsibility objectives, Ende Transmisión, a subsidiary of Ende Corporation, began in September the second phase of the educational program “Together We transmit energy ”, whose objective is to provide information that enables the understanding of operation of the electrical system in Bolivia and also allows to raise awareness about the Be careful that both children and adults must have in relation to electricity and towers high voltage.

    nf_04102022_2

    Once the program that will be developed in schools in the rural and urban area of the Departments of Oruro, Cochabamba, Santa Cruz and La Paz, will benefit more than 140 units Educational from the national territory, 10,000 students and 600 teachers directly, as well as to the parents and people from these communities indirectly.

    The company carries out this activity 19 years ago in the rural areas of Bolivia, because it considers vital importance the dissemination of educational information about a service that is essential for the Country development: electricity.

  • UNICOM/ENDE Transmisión: Ende Transmisión made for its personnel workshop on law against the Racism and all forms of discrimination

    Yesterday Wednesday, September 21, Ende Transmission made for its workers in a way face -to -face and/or through virtual platform the workshop on “Law No. 045, Law against Racism and all forms of discrimination ”, with the aim of eliminating racism behaviors and all forms of Discrimination for the prevention of crimes of racism and all forms of discrimination in the exercise of functions.

    nf_4102022_1
  • August 1, 2022
    UNICOM/ENDE CORPORATION: Despite debts of the Government of Tarija and Sear, it is transmission Continues to guarantee electric service

    The general manager of the Ende Transmission, Ing. Filiberto Soto reported on the debts that They maintain the Departmental Autonomous Government of Tarija (GADT) and the Electric Services Company of Tarija (Setar), the same that jointly rises to more than 185 million Bolivians. “Currently the Government of Tarija owes us more than 132.8 million and reversing more than 52.4 million From Bolivians, even so, we continue working for Tarija, without harming the population. ”

    nf_01082022_4

    Soto recalled that in December 2014, Ende Transmisión signed a contract with the Autonomous Government Departmental of Tarija for the execution of the project Construction and Technical Adaptation to the System National interconnected (SIN) of the Central Tarija system, which included the extension of the Tarija, Villa Abaroa and La Tablada substations, in addition to the construction of the lines of Transmission in 115 kV Tarija – Villa Abaroa of 6.21 km and Villa Abaroa – La Tablada of 5.56 km.To date are completed, energized and in service all the facilities of the project, Except for the 115 KV Villa Abaroa – La Tablada line, which was paralyzed by the neighbors.

    “To date, the GAD de Tarija has a pending debt of Bs. 132,806,124.55 and according to a report presented details that until July 3, 2022 the global progress of the aforementioned projects It is 99.32%.Despite the economic damage caused to the transmission that operates in the system National interconnected, the service has been guaranteed uninterrupted 365 days of the year, for the benefit of the electrical and country sector as a whole, ”said the authority. The manager indicated that due to breach of payment, and with the desire to keep the good Relations with GADT, in December 2016, Ende Transmission signed a modifying contract that stipulates a new payment plan and delivery time, “but as a result of the repeated breaches by the GADT, in September 2018, in the transmission was forced to Intend an administrative contentious demand. ”

    About Setar, Soto reported that the debts of said company affect “interconnection projects completed in the subsystems of Yacuiba, with a debt of Bs. 5,066,265.79 and Villa Montes with Bs. 11,199,863.81;In addition to toll debt in the interconnection trunk system (STI) by part of Setar, for a total amount of Bs. 36.205.055.42, which includes the Central Tarija system and the Yacuiba and Villamontes systems respectively ”.

    The manager recalled Ende’s commitment to the department of Tarija, stressed that “ currently operates in the national interconnected system uninterruptedly guaranteeing the Access to electricity 365 days a year, for the benefit of the Tarijeños and Bolivians. ”

  • UNICOM/ENDE TRANSMISIÓN: As part of your social responsibility, it is ENDE Transmisión culminates First phase of risk prevention program in rural areas of the country

    Fulfilling one of its Social Responsibility objectives, ENDE Transmisión, a subsidiary of Ende Corporation, culminated in June the educational program “Together we broadcast energy”, in Schools of the rural and peri -urban area of the departments of Beni, Potosí, Sucre and Tarija.

    nf_01082022_3

    The objective of this program is to provide information that enables the understanding of operation of the electrical system in Bolivia and that also allows to raise awareness about the care that so much Children as adults, should have in relation to electric laying and high voltage towers.

    With the first phase of the program, more than 70 educational units of the national territory, more than 3,100 students and 240 teachers directly, as well as to parents and people from these communities indirectly.

    The company carries out this activity 19 years ago in the rural areas of Bolivia, because it considers vital importance the dissemination of educational information about a service that is essential to The development of the country: electrical energy.

  • UNICOM/ENDE: It states about wind energy and the interconnection of Camiri al Sin in 6th. Plurinational multisectoral fair

    The National Electricity Company Ende Corporation, through its Subsidiaries Ende Corani and Ende Transmisión, participated this Saturday, July 9, the sixth multisectoral plurinational fair, organized by the Ministry of the Presidency through the Vice Ministry of Coordination and Management Government in the municipality of Camiri of the department of Santa Cruz.

    nf_01082022_2

    Ende Corani workers exposed in their informative stand about the importance of generation of wind energy in Bolivia, which today reaches 135 MW installed to the interconnected system National (SIN), through 40 wind turbines located in three wind farms located in Santa Cruz, and a wind farm located in Cochabamba.

    For its part, the company ENDE TRANSMISIÓN highlighted the construction and maintenance work of high voltage transmission lines that allow electrical interconnection throughout the country, thus such as the execution of important projects that connect populations to the interconnected system National (SIN), as is the case of the Camiri Al Sin interconnection project, which consists of the sectioning of a transmission line that starts from the Padilla substation, located in the Intermediate Substation of Monteagudo and concludes in the substation of Camiri, whose length Approximate of the line line is 125 km.

    Multisectoral fairs are informative spaces of which the 17 ministries participate in through their dependent entities and companies, in order to socialize their work and benefit that this has for the population as a whole.

  • UNICOM/ENDE CORPORACIÓN: Electric transmission projects in Tarija, La Angostura and Bermejo They register more than 95% progress

    UCOM-MHE-ENDE-AETN-07-07-2022.- The Deputy Minister of Electricity and Alternative Energies, Edgar Caero, the vice president of the National Electricity Company (Ende Corp.), Mauricio Arevey, the Ende Transmission Manager, Filiberto Soto, and the Director of the Supervisory Authority of Nuclear electricity and energy (AETN), Eusebio Aruquipa, verified this Thursday that the projects of electric transmission that are built in Tarija, La Angostura and Bermejo are in their Final stretch with more than 95% progress and it is expected that in the following weeks they will be inaugurated for Get into operation.

    nf_01082022_1

    “Bermejo will connect to the National Interconnected System (SIN), its electrical energy will no longer depend of an isolated system, and will receive electricity from all over Bolivia, from the centrals thermal, hydraulic, wind and solar that we have in the country and growth and development of this region, ”said Vice Minister Caero at a press conference after Perform an inspection of the works.

    The authorities first inspected the transmission line 115 kilovolts (KV) Tarija – the Angostura, which will have a length of 44.17 kilometers (km) and that already has 96% advance. This project will allow the connection to the new window generation central La Ventolera and will provide an energy withdrawal node through the construction of the new 115 kV substation Angostura.

    Subsequently, they verified the advance of the 115 kV transmission line La Angostura – Bermejo, which Record 95% and will allow the connection of the isolated electrical system of Bermejo, improving quality of the electric service in the region for the benefit of that population of Tarijeña.The project includes the Construction of a simple list of transmission of 138.10 km in length and construction of the new electrical substation for Bermejo.

    The National Government invests approximately BS182 million for these projects, within the framework of the Universalization policy of basic services.

    In turn, Aruquipa said that approximately 10,500 families will benefit from These projects, which guarantee a reliable electrical service.

  • June 29, 2022
    UNICOM/ENDE CORPORACIÓN: ENDE CORPORACIÓN present in Feicobol with a stand that shows the Productive chain of the electricity industry

    06/20/2022.- ENDE CORPORACIÓN participates in the Cochabamba 2022 and today 17 of June inaugurated its informative stand called “The Journey of Energy”, which shows the chain productive of the electricity industry in the country.At the inauguration the President of the National Electricity Company (Ende Corporation), Manuel Valle Vargas, the Vice President of Ende, Mauricio Arevey Mejía, authorities of the electricity sector, managers of Ende subsidiaries and guest audiences.

    nf_29062022_1

    In the Stand of ENDE CORPORACIÓN, the experience called Electric Power is lived, It deals with an audiovisual description that allows to know the eco -amigable work of the company considered fundamental pillar of national development and with international projection.

    The exhibition allows to show a space of the production chain of the electrical industry, where You can see through several stops and playful rooms where electricity is generated, how it is transported and how it is administered to reach homes, industries and public services.It most important is that visitors participate playfully, entertain, learn and recognize The importance of the work carried out by ENDE CORPORACIÓN for the benefit of society as a whole.

    ENDE CORPORACIÓN is committed to the environment and therefore, in the modern stand it presents the Information on the generation of electrical energy in centrals capable of obtaining electricity to from renewable primary energies such as water, wind, solar radiation and heat of the subsoil.Mother Earth’s protection is everyone’s task. ENDE CORPORACIÓN has shown high commitment to society in the execution of fully respectful projects with the environment as are those that incorporate renewable energies into the energy matrix:

    • Wind power (Qollpana 27 MW, El Dorado 54 MW, San Julian 39,6 MW y Warnes 114,4 MW).
    • Solar energy (Yunchará 5 MW, Uyuni 60 MW, Oruro 100 MW y Cobija 5,2 MW).
    • Hydroelectric power (San José I y II 124 MW, Misicuni 120 MW, Ivirizu and Miguillas at building).
    • Energía geotérmica (Pilot plant in Laguna Colorada 5 MW).

    The exhibition will allow to socialize that the ENDE CORPORACIÓN is a company that has an impact within The national economy works for Bolivians, not only guaranteeing electrical energy for homes and industry;Its profits return to the population in the form of projects of Rural electrification and social bonds.

  • UNICOM/ENDE CORPORACIÓN: ENDE CORPORACIÓN present in Feicobol with a stand that shows the Productive chain of the electricity industry

    06/20/2022.- The General Manager of Ende Transmisión, engineer Filiberto Soto, reported on the projects that have been executing in the municipality of Bermejo (Tarija), highlighted the interconnection of said municipality to the national interconnected system (SIN), with two important projects: line of Transmission 115 kV Tarija – La Angostura and the Transmission Line 115 KV La Angostura – Bermejo, by which the immediate response to electricity cuts in the area will be guaranteed.

    nf_29062022_2

    “The execution of these important projects are framed in the deadlines declared in the Medium -term programming (PMP) of the National Cargo Office (CNDC), therefore all The activities carried out by the ENDE Transmisión are being fulfilled in the established deadlines ”, Soto said, who also stressed that these projects seek to “reaffirm Ende’s commitment ENDE Corporación to maintain a high quality service, offering society and the country in its set the highest added value, occupying an avant -garde position in the transport of electric systems”.

    The 115 kV Tarija – La Angostura transmission project has a cost of BS49.966.953, It currently has a general advance of 93%, which will allow the connection to SIN of the new central of wind generation the ventolera and will provide an energy withdrawal node through the Construction of the new 115 kV substation La Angostura.

    The construction comprises a transmission line at 115 kV, of a total length of 44.17 km, a Incomplete double list section at the exit of the Angostura substation and the other section in simple Terna;In addition to the extension of the existing Tarija and construction substation of the new Substation La Angostura with all the respective general facilities.

    For its part, the 115 kV La Angostura – Bermejo transmission project has a cost of BS132.145.622 and a general advance of 90%, will allow the connection of the isolated electrical system of Bermejo (which currently generates energy from a system based on generation units diesel thermoelectric plant) to the national interconnected system, enabling an improvement of the Electrical supply conditions for the economic development of this important region.

    The project includes the construction of a simple list of transmission of 138.10 km of length and construction of the new Bermejo substation with all general facilities respective.

  • June 1, 2022
    UNICOM/ENDE TRANSMISIÓN: Ende Transmisión implements breastfeeding room for your workers

    On Friday, May 27, on the occasion of Mother’s Day, Ende Transmisión made the Inauguration of the breastfeeding room for the workers of the company that so They require, as an initiative of social responsibility integrated to the harmony program, which seeks Create favorable conditions for all the institutions of the institution.

    news_featured_01062022_1

    This support program, promotion and protection of the breastfeeding of Ende Transmisión responds to the need for compliance with the General Labor Law, Article 62, of breastfeeding MaternalFrom the social perspective and human development, it contributes to the achievement of one of the SOCIAL DEVELOPMENT OBJECTIVES (SDG) to improve the nutritional status of the child, the prompt recovery of the working mother and to reduce the morbidity and mortality rates of the minors of five years and their mothers.

    Beyond the tangible and intangible benefits, doctors, psychological and development, Related to breastfeeding, there is in current legislation the Supreme Decree 0115, of 06 of May 2009, art.1, which mentions textual “This decree is intended to establish the Regulatory provisions in order to promote, support, promote and protect breastfeeding to guarantee the exercise of childhood right to receive the best food and women breast-feed”.This decree is applicable to companies with more than 50 workers.

  • UNICOM/ENDE TRANSMISIÓN: ENDE Transmisión performs training for security personnel, Company cleaning and gardening

    On Friday, May 20, a training on quality was carried out in Ende, medium Environment, Occupational Health and Safety, and Social Responsibility for office staff central that develops its work in the areas of gardening, cleaning and safety, in order to that they can know and/or refresh their knowledge regarding these issues that are part of the international certifications that the company possesses.

    news_featured_01062022_1